Al-Ammara Gas Turbines Power Project

 In projects

in 2016 MOE call us to meet  STX company on site to support them during energizing units then synchronizing units with grid 400kv system. they faced problem during synchronizing unit gird get trip unit by differential protection of step-up transformer after an inspection found setting relay parameters (wrong), polarity current transformer need modifying in the wiring of the secondary circuit.